After extensive rot repair on an additional Bella Vista courtyard, HABC has made progress on rebuilding the deck. We have also started the resident room remodels, which are simultaneously remodeled as the Westcoat deck waterproofing is installed. Check out some video of a bit of the action here

 

HABC has started work on an 1,800 sq ft kitchen flooring project for the Bella Vista care center community. This new floor will provide Bella Vista with quarry tile and sanitary covering throughout the area. We have been achieving this work in the evening and early custom essay morning hours, this allows the staff to continue serving the care center residents without interruption.

Two staff restrooms and a new tub/shower room are complete. All restrooms have been upgraded to meet http://custom-essay-service-help.co.uk current ADA standards. Additional pictures to come as more of this multi phased project is completed.

Construction of the elevator at St. James Manor assisted living community is pictured above. Progress continues this week as the elevator unit is shipped, the last of the steel components are completed and all the flagstone is installed. Looking good!